Motorists will be well-advised to avoid the intersection of Mass Ave at College Avenue and St. Clair Street beginning Monday.
That’s because – after months of concern voiced by Mass Ave stakeholders as well as the Chatham Arch Neighborhood Association – the intersection will be closed for a major overhaul.
Contractors for the Indianapolis Department of Public Works will begin construction as part of a project to improve safety and resurface pavement, a DPW press release announced Oct. 9. Weather permitting, construction is expected to be completed by late November. Businesses will remain accessible throughout construction.
The project incorporates permanent safety improvements into a previously planned resurfacing project. The improvements were developed following community conversations in October 2025 about safety concerns at the intersection, including the need for permanent solutions to better protect vulnerable road users following a fatal crash involving a pedestrian and an intoxicated driver.
Planned improvements include:
* Six-inch raised curbing and modular curb extensions.
* Increased on-street parking along College Avenue.
* Crash-rated bollards, rated to withstand impacts at speeds up to 30 mph, along the Indianapolis Cultural Trail.
* Traffic signal adjustments and relocations.
* Lane reconfigurations.
* New pavement markings and striping.
The project is being coordinated with community partners at the Indianapolis Cultural Trail to improve access and incorporate permanent safety features that better protect people walking and biking through the area.
This project follows past safety projects the area, such as the two-way conversion of College Avenue between Market Street and Massachusetts Avenue in early 2024.
City officials said these safety improvements are paramount as Indianapolis seeks to eliminate traffic fatalities as part of the city’s Vision Zero initiative. On Indianapolis roadways, fatal crashes decreased by nearly 16% from 2024 to 2025. Fatal crashes have declined by nearly 30% compared to the peak of the pandemic in 2021, bringing fatal crashes back to pre-pandemic levels. Indy DPW and the City of Indianapolis remain focused on accelerating and sustaining the positive downward trajectory.
Construction and traffic impacts
During Phase 1, crews will resurface the east side of College Avenue between East 10th Street and the Massachusetts Avenue. Through traffic on Massachusetts Avenue will be fully closed at the intersection of College Avenue and St. Clair Street.
Access to East St. Clair Street and the northeast portion of Massachusetts Avenue at the intersection will also be restricted during this phase.
Drivers should plan for the following access changes and detours:
* Resurfacing construction will take place on the east side of College Avenue from 10th Street to the Massachusetts Avenue intersection
* Access will not be available on eastbound St. Clair Street or northeast-bound Massachusetts Avenue during this period.
* Access to the Indianapolis Cultural Trail will be maintained, except when the crosswalk at the intersection is actively under construction.
* Flaggers will be on site to direct trail users around the work area and safe detour routes.
* Through traffic on College Avenue will have access on westbound St. Clair Street and southeast-bound Massachusetts Avenue.
* Additional access will be available on 9th Street into the Bottleworks/Garage area.
* East St. Clair Street & Mass Ave. detour: Traffic will be redirected via East 10th Street to South Bellefontaine Street to Davison Street.
Drivers, pedestrians and cyclists are encouraged to use caution near the work zone, follow posted detours and directions from construction personnel, and allow additional time when traveling through the area.
The permitted construction period represents the time during which the contractor is authorized to close roads or limit access as needed and does not mean the intersection will remain fully closed for the entire duration.
For the safety of everyone traveling through the area, Indy DPW encourages the public to remain alert to changing traffic patterns and follow all posted signs throughout construction.
To learn more about traffic safety initiatives in Indianapolis, visit Indy.gov/VisionZero.